Cited from real sources 6 min read Written by Arun Agrahri Updated October 2026

A framework by Gary Klein

Gary Klein's Premortem: How to Run One in 20 Minutes

A premortem is a 20-minute exercise in which a team assumes its plan has already failed and spends two minutes writing down every reason why. The psychologist Gary Klein invented it in the late 1980s for project kickoffs at his own company. Because the failure is stated as certain, people stop defending the plan and start competing to find its weakest point.

Why it works

The way you show you're smart in a pre-mortem is the quality of the items that you generate.

In a normal kickoff, raising a problem costs you something. Klein's crystal ball changes what the room rewards, so the doubts people were sitting on come out first.

Gary Klein The Knowledge Project Watch at 57:39

The framework

Move the post-mortem to the front

In the late 1980s Klein ran a research company. Most of its projects went well and a few failed. After each failure the team held an after-action review and found what they should have done differently. Then Klein asked why they waited until the end. A physician's post-mortem helps the doctor and the family and does nothing for the patient, so he moved the review to the kickoff meeting.

His change is in how the question is put. The usual kickoff ends with "Does anybody see any problems?" and Klein says nobody answers. The team has just spent an hour on the plan, everyone is impatient to start, and naming a flaw can cost you. A premortem takes the hedge away. The facilitator looks into an imaginary crystal ball, six months or a year out, and reports that the project has been a disaster. The ball is never wrong, though it does not say why the project failed.

It's not an issue of what can go wrong. We're dealing with a crystal ball that has showed that the plan has failed.
Klein, on the most common mistake Watch at 59:56

A risk review asks what could go wrong, which invites a polite guess. A premortem says the project failed and asks for the explanation, so each person's experience goes to work on a story. In a 2010 study by Veinott, Klein and Wiggins, 178 students critiqued a university's plan for a flu outbreak. The group that ran a premortem lost the most overconfidence, more than the groups that critiqued the plan or listed pros and cons.

Practice

How do you run a premortem?

Klein's version takes about 20 minutes at the end of a kickoff meeting, in six steps.

1

Run it after the plan is settled.

Wait until everyone knows the plan and their role in it. Klein uses the last 20 minutes of the kickoff, because people who know the plan find better flaws.

2

State the failure as fact.

Pick a horizon of six months or a year. Say the project failed badly and that the crystal ball does not lie. Do not ask what might go wrong.

3

Give everyone two minutes, alone, on paper.

Klein tested the length. At one minute people were still writing when time ran out, and past two minutes many ran dry. Writing alone first matters too: he points to research showing group brainstorming does not produce more or better ideas.

"in two minutes write down all the reasons why this project failed"

19:39
4

Go around the room, leader first.

Each person reads out the top item on their list that nobody has said yet. Go around a second time, sometimes a third, and keep the pace quick.

"You start with the team leader, to set an example of being candid."

Psychology Today, 2021
5

Spend two more minutes on what you will do.

A long whiteboard of failure can flatten a team, so Klein added a closing round.

"take another two minutes for each member to identify actions s/he can take to address some of the items."

Psychology Today, 2021
6

Rate what is left.

In a later change, Klein and Marcus Dimbleby have the team rate each problem for likelihood, impact and how easy it is to prevent. The whiteboard becomes a priority list.

Boundary conditions

When does a premortem fail?

Asked at the New York Fed what conditions a premortem needs, Klein said he has never seen one fail. He adds a caveat of his own. His evidence for the effect on team culture comes from his own companies, and he has not followed other organizations to check. What he has catalogued, with Paul Sonkin and Paul Johnson, are the ways people run it wrong.

with a premortem, with the leader going first and voicing a possible problem that nobody had mentioned before, that sets the stage. Instead of saying I want you to feel psychological safety, you're now demonstrating it. You're now living it.
Klein, on why the leader goes first Watch at 30:49

This is why the leader goes first. When a leader gets cold feet and says they just want to hear what everyone else has, Klein says the room turns dangerous and only the leader is protected. It is also why he prefers a premortem to appointing a devil's advocate. Once one person is the official critic, everyone else stops criticizing, and nobody can tell whether the critic means it. In a premortem the critics are the people who will carry out the plan, so their concerns are real.

Works best when

  • The project has a deadline and a deliverable
  • The team has heard the whole plan and knows its roles
  • Everyone writes alone before anyone speaks
  • The leader names a real flaw first

Fails when

  • Someone asks "what could go wrong?" instead of stating that it failed
  • One senior person reads out a whole list while the rest listen
  • People talk at length and the energy drains out
  • The list stays on the whiteboard and nobody owns an action

The same list can become your stopping rules. Annie Duke's kill criteria take the warning signs from it and attach an action to each one before launch, so the team knows in advance what will make it stop.

Primary sources

Where Klein discusses this

Klein has told the premortem in the same steps for years, so the details are easy to check. The 2022 Knowledge Project interview with Shane Parrish is the fullest version, including the three common mistakes. The 2023 conversation at the New York Fed covers why the leader goes first and how a premortem compares with a devil's advocate. He also wrote it up for Harvard Business Review in 2007 and for Psychology Today in 2021.

Where experts disagree

Where operators disagree: does a premortem change the plan?

Gary Klein

built the premortem to fix the plan at kickoff: the failure list cuts the team's overconfidence, and a closing two-minute round on what each person will do leaves a stronger plan and a more resilient team.

Annie Duke

counters that running a premortem rarely changes the plan much, and that its real output is kill criteria: the signals that mean stop, each tied to an action before anyone is invested.

It turns on whether the plan can still move. At a kickoff, before roles and budget are locked, Klein's version pays because flaws get fixed. Once you are committed, sunk cost is the risk, so turn the same list into Duke's stopping rules.

Useful? Send it to whoever runs your next kickoff.

Want the full playbook?

Get 457 strategic thinking frameworks.

89 frameworks 125 rules 235 heuristics & principles 11 operators

From Annie Duke, Donella Meadows, Ray Dalio, and 8 more. Drop one .md into Claude, Cursor, or ChatGPT. Your AI cites practitioners, not guesses.

See the pack

Instant .md download · One-time purchase · No subscription

New experts every week

Know when the next expert lands.

Gavel adds new operators to the database every week, each one with cited frameworks you can check and a note on where they disagree with the others. You found this page by searching. Get the next one by email instead.